Negotiating Variations and Change Orders in Construction Contracts
Negotiation

Negotiating Variations and Change Orders in Construction Contracts

By Ashraf Ibrahim El Desoky · Jul 27, 2026 · 8 min read

Negotiating Variations and Change Orders in Construction Contracts

Understanding Variations in Construction

Variations (change orders) are modifications to the scope, design, or execution of work after contract award. Under FIDIC Clause 13, the Engineer may issue variations, and the contractor is obliged to execute them. The negotiation challenge is agreeing on fair valuation.

Variation Valuation Methods

1. Bill of Quantities Rates

When the variation is similar to BOQ items:

Apply existing BOQ rates directly, Adjust for quantity: if quantities change by more than 10% (FIDIC Clause 12.3), rates may be re-negotiated, and Pro-rata adjustment for partial similarity.

2. Derived Rates

When work is similar but not identical to BOQ items:

Break down into constituent elements: labour, material, equipment, overhead, Adjust each element for the specific variation, and Example: BOQ has "concrete Grade 30 in columns at $200/m3" — variation requires "concrete Grade 40 in walls" — adjust material cost for higher grade, adjust labour for wall formwork vs column formwork.

3. New Rates

When work is entirely different from BOQ items:

Obtain market quotations from subcontractors/suppliers, Use published rate guides (RICS, local authorities), Apply contractor's actual cost records from similar work, and Add agreed overhead and profit percentage (typically 10-15%).

4. Daywork

When work cannot be measured or valued:

Use agreed daywork rates: labour per hour, equipment per hour, materials at cost plus percentage, Record on signed daywork sheets with hours, equipment, and materials, and Consultant must sign daily — unsigned sheets may be rejected.

Negotiation Strategy for Variations

Step 1: Define Scope Precisely

Ambiguity is the enemy of fair valuation:

Use detailed scope sheets with drawings, specifications, and quantities, Define what is included and excluded, Agree on acceptance criteria before pricing, and Avoid "lump sum for all extras" — itemise for transparency.

Step 2: Establish the Valuation Basis

Agree which method applies (BOQ rates, derived rates, new rates, daywork), If new rates: agree the cost breakdown structure and overhead percentage, If daywork: agree rates before work starts, not after, and Reference similar BOQ items or previous variations as benchmarks.

Step 3: Assess Time Impact

Does the variation affect the critical path?, Use schedule impact analysis (time impact analysis or windows analysis), Negotiate extension concurrently with cost — do not leave time for later, and Document agreed extension in the variation order.

Step 4: Negotiate the Package

If multiple variations are pending, negotiate as a package, Trade higher rates on some items for lower rates on others, Include disruption impact in the package rather than as a separate claim, and Agree a global figure with itemised breakdown for record.

Common Variation Disputes and Resolution

Dispute 1: "The rate is too high"

Resolution: Open-book audit — review contractor's actual cost records, Compare with market rates from other suppliers, and Use independent QS assessment.

Dispute 2: "This is not a variation — it was in the original scope"

Resolution: Refer to contract drawings and specifications, Compare scope at tender vs current requirement, and If genuinely new work, it is a variation; if clarification of existing scope, it is not.

Dispute 3: "Overhead and profit percentage is excessive"

Resolution: Refer to contract — if contract specifies O&P percentage, apply it, If silent, use industry standard: 10-15% for direct work, 5-7.5% for subcontracted work, and Negotiate lower O&P for large-value variations (economies of scale).

Dispute 4: "Concurrent delay means no extension"

Resolution: Apportion delay between variation and other causes, Only variation-caused delay on critical path qualifies for extension, and Use schedule analysis to isolate variation impact.

Best Practices for Variation Negotiation

Issue variation instructions promptly — delay creates cost escalation, Negotiate rates before work starts, not after completion, Maintain a variation log with status, value, and time impact, Cap cumulative variations — if variations exceed 15-20% of contract value, consider re-tendering, and Include variation costs in monthly payment certificates — do not accumulate.

← Back to Articles