Negotiation Preparation and Planning for Construction Professionals
The 80/20 Rule of Negotiation
Eighty percent of negotiation success comes from preparation; twenty percent from the negotiation itself. Yet most construction professionals spend minimal time preparing, relying instead on experience and improvisation. This article provides a structured preparation framework.
Phase 1: Information Gathering
1. Know Your Position
- What exactly do you want? Be specific: "A 15-day EOT plus $75K in delay costs for the design revision delay"
- What is your justification? Contract clause, schedule analysis, cost records
- What is your BATNA? DAB, arbitration, accept the situation, escalate to senior management
- What is your reservation price? The minimum you will accept
2. Know Their Position
- What do they likely want? Based on their actions, correspondence, and past behaviour
- What are their constraints? Budget limits, schedule pressures, board approvals, public scrutiny
- What is their likely BATNA? Replace you, litigate, delay the project, accept the situation
- What is their likely reservation price? Based on their budget and alternatives
3. Know the Context
- What is the project status? Early, mid, or late stage affects leverage
- What is the relationship history? Previous disputes, successful collaborations
- What external factors apply? Market conditions, regulatory changes, public attention
- What are the time constraints? Upcoming deadlines, financing milestones, handover dates
Phase 2: Stakeholder Analysis
Map all stakeholders:
- Primary parties: You, the other party, the decision-makers on both sides
- Secondary parties: Consultants, subcontractors, suppliers, authorities, financiers
- Influencers: Senior management, board members, end users, public
For each stakeholder, assess:
- Interest level: How much do they care about the outcome?
- Influence level: How much can they affect the outcome?
- Position: Are they supportive, neutral, or opposed?
- Needs: What do they need from the negotiation outcome?
Phase 3: Interest Mapping
Create a two-column table:
| Your Interests | Their Likely Interests |
|---|---|
| Fair compensation for additional work | Budget control |
| Schedule recovery | On-time completion |
| Maintaining relationship | Quality assurance |
| Avoiding dispute escalation | Avoiding claims |
| Cash flow improvement | Cost certainty |
Identify:
- Shared interests: Both want project completion, safety, quality
- Compatible interests: Your schedule recovery = their earlier handover
- Conflicting interests: Your higher price = their higher cost
Phase 4: Strategy Development
1. Set Your Objectives
- Ideal outcome (target): The best realistic result
- Acceptable outcome: A fair result you can live with
- Walk-away point: Below this, exercise your BATNA
2. Develop Your Opening
- Will you open first or let them? (Opening first allows anchoring)
- What will your opening position be? (Ambitious but credible)
- What supporting data will you present? (Documentation, analysis, benchmarks)
3. Plan Your Concessions
- List all items you can concede and their value to the other party
- Order concessions from lowest cost to highest cost
- Never concede without getting something in return
- Plan the "if...then" structure: "If you accept X, then I will concede Y"
4. Anticipate Their Tactics
- What tactics will they likely use? (Anchoring, nibbling, good cop/bad cop, deadline pressure)
- How will you respond to each? Prepare specific responses
- What questions will they ask? Prepare honest, strategic answers
Phase 5: Team Preparation
Assign roles:
- Lead negotiator: Presents the main position, makes opening and closing
- Technical expert: Provides technical details, answers specialist questions
- Note-taker: Records agreements, tracks concessions, documents the session
- Observer: Watches body language, identifies tactics, advises during breaks
Pre-meeting briefing:
- Review objectives, strategy, and roles
- Agree on signals for requesting a break
- Discuss what information can and cannot be shared
- Prepare fallback positions for each major issue
Phase 6: Logistics
- Venue: Neutral ground is best; if not possible, your office gives slight advantage
- Seating: Round table for collaborative; opposite sides for competitive
- Timing: Avoid late afternoon (fatigue); morning is optimal for complex issues
- Materials: Bring copies of all documents, a printed agenda, and a term sheet template
- Refreshments: Provide quality refreshments — it sets a collaborative tone
- Technology: Agree on whether phones/laptops are allowed during the session
The Negotiation Preparation Checklist
- [ ] Objectives defined (target, acceptable, walk-away)
- [ ] BATNA developed and evaluated
- [ ] Other party's interests and constraints analysed
- [ ] Stakeholder map completed
- [ ] Interest mapping done (shared, compatible, conflicting)
- [ ] Opening position prepared with supporting data
- [ ] Concession plan prepared (ordered, conditional)
- [ ] Anticipated tactics and responses prepared
- [ ] Team roles assigned and briefed
- [ ] Logistics arranged (venue, timing, materials)
- [ ] Agenda drafted and shared (or held for the meeting)